Case Study – Littleport
Project Overview
Client:
Barratt Redrow PLC
Location:
Littleport
Roads & Sewers:
1.4km
Plots:
90
The Challenges
Our Delivery
- Major and complex infrastructure works for roundabout construction
- Accelerated programme to support client's sales launch
- Coordination of works around live services to facilitate the connection of the rising main to the pump station
- Large stormwater attenuation pond construction with associated noise bund to provide acoustic screening
- Delivered A10 roundabout works achieving seamless integration into the existing network.
- Strategically planned traffic management to allow for safe working and site access adjacent to live roads.
- Efficiently sequenced works to achieve delivery of critical infrastructure within compressed timescales to support an accelerated sales launch for the Client.
- Avoided service outages and safety incidents when installing and commissioning the pump station and rising main around live services.
- Adhered to strict drainage performance and environmental requirements during the construction of the stormwater attenuation pond and associated noise bund.
- Handover of plots completed, providing access for follow-on trades and superstructure construction.